Managing Key Tracking Dates for a Template
The Key Tracking Dates window allows you to set up planned start and finish deadlines for a template. Some example milestone dates include Information Received, Preparation Complete, or Review Complete. You can also set methods for how each milestone date is set.
All the milestone dates assigned to the template are shown in the Milestone dates section at the bottom of the Key Tracking Dates window for the template.
To manage template key tracking dates, do the following:
- Open the Templates list.
- Select a project template, and then click. You can also right-click and select Open from the menu.
- Click Key Tracking Dates on the navigation panel.
-
Set planned start and finish deadlines for a project template. The method used to set the project deadlines depends on the answer to the Calculate planned dates question on the Project Template - General Information window.
To manage project deadlines, do one of the following:
-
If your project is not tracking milestone dates, continue to the last step. Otherwise, do one of the following to add or remove milestone dates listed in the grid:
- If no milestone dates are listed in the Milestone dates section, or you would like to add to the grid, click Milestone Dates on the button bar to list all milestone dates inherited from the project type but not selected for the template.
- Select the milestone dates to assign to the template on the Milestone Dates window. For more information, see Using the Milestone Dates Window.
- Select an unlocked milestone date and click Remove in the button bar to remove the selected row from the grid.
-
Confirm or update the method to set the project milestone dates. Do one of the following:
- Enter the milestone date.
- Select a milestone date.
- Select Staff entry in the Date is Set By column.
- Enter the milestone date in the Date column.
- Set the date by completion of a workstep (available if the project template is set to use worksteps).
- Select a milestone date.
- Select Completion of workstep in the Date is Set By column.
- Select a project workstep from the Workstep column. The available worksteps are those that have not been selected to set other milestone dates.
- Explain the lock and unlock buttons.
- Click one of the Save buttons or Cancel.